Progress Report as of April 2026
Residence 1 (Near Completion)
Stair systems complete: treads, landings, and integrated lighting
Cabinetry updates complete: ski room, bunk room, mudroom, bar
Trim + touch-ups underway
Punch list + final cleaning to begin once railings are complete
Residence 2 (Finishing Stage)
Shower enclosures + majority of mirrors installed
Plumbing fixtures + electrical trim nearing completion (LED install underway)
Final drywall + paint in stairwell in progress
Installation of stair treads and landings has begun
Residence 3 (Interior Finishes Well Underway)
Cabinetry installed + slab countertops set
Fireplaces complete (great room + upper den)
Reclaimed wood feature wall + ceiling in primary bedroom
Trim, doors, and custom staining in progress
Closet systems installed
Mechanical trim (plumbing, electrical, HVAC) underway
Residence 4 (Transitioning to Finishes)
Drywall complete; ceilings painted + walls primed
Wood ceilings underway (great room + mezzanine)
Fireplace stonework + elevator installation in progress
Wood flooring install has begun
Interior doors + trim has begun
Cabinetry install to follow
Site & Exterior Progress
Stone veneer complete on Residence 4 front façade; crews moving across Residences 1–3
Snowmelt + flagstone complete at Residence 3 (deck + walkways); hot tub patio nearing completion
Steel railing components installed across decks
Soffit + stucco work ongoing
Driveway planning underway
Crane removal scheduled for mid-May
Check back here for monthly construction updates of the project