Progress Report as of September 2026
40 RED SPRUCE LANE | NEARING COMPLETION | SOLD
• AV installation is underway, including TVs, outdoor speakers and network systems
• Final cleaning is complete and punch-list work continues
• Mechanical, electrical, plumbing, fire sprinkler and blower door inspections have passed
42 RED SPRUCE LANE | NEARING COMPLETION | AVAILABLE
• Carpet, cabinet hardware and final cabinetry adjustments are complete
• Protection has been removed and the Residence has received its initial final cleaning
• Mechanical, electrical, plumbing and blower door inspections have passed
• Punch-list work and final touch-ups continue
44 RED SPRUCE LANE | FINISHING STAGES | AVAILABLE
• Backlit vanity slab installed
• Metal railings complete, with railing glass now in fabrication
• Patio heaters installed
• Garage drywall, paint and epoxy flooring complete
• Final elevator inspection scheduled for September 21
• Punch-list work and final touch-ups continue
46 RED SPRUCE LANE | INTERIOR FINISHES UNDERWAY | AVAILABLE
• Appliances delivered and staged for installation
• Slab countertops installed, with kitchen backsplash slabs continuing next week
• Interior metal railings underway
• Plumbing and electrical trim-out in progress
• Family room bar backsplash complete
SITE + EXTERIOR
• Driveway insulation and concrete sub-slab work complete
• Garage doors installed at 40 & 42, with 44 scheduled next
• Snowmelt boiler work complete
• Front deck railing complete at 40 and underway at 42
Check back here for monthly construction updates of the project