Progress Report as of April 2026

Residence 1 (Near Completion)

  • Stair systems complete: treads, landings, and integrated lighting

  • Cabinetry updates complete: ski room, bunk room, mudroom, bar

  • Trim + touch-ups underway

  • Punch list + final cleaning to begin once railings are complete

Residence 2 (Finishing Stage)

  • Shower enclosures + majority of mirrors installed

  • Plumbing fixtures + electrical trim nearing completion (LED install underway)

  • Final drywall + paint in stairwell in progress

  • Installation of stair treads and landings has begun

Residence 3 (Interior Finishes Well Underway)

  • Cabinetry installed + slab countertops set

  • Fireplaces complete (great room + upper den)

  • Reclaimed wood feature wall + ceiling in primary bedroom

  • Trim, doors, and custom staining in progress

  • Closet systems installed

  • Mechanical trim (plumbing, electrical, HVAC) underway

Residence 4 (Transitioning to Finishes)

  • Drywall complete; ceilings painted + walls primed

  • Wood ceilings underway (great room + mezzanine)

  • Fireplace stonework + elevator installation in progress

  • Wood flooring install has begun

  • Interior doors + trim has begun

  • Cabinetry install to follow

Site & Exterior Progress

  • Stone veneer complete on Residence 4 front façade; crews moving across Residences 1–3

  • Snowmelt + flagstone complete at Residence 3 (deck + walkways); hot tub patio nearing completion

  • Steel railing components installed across decks

  • Soffit + stucco work ongoing

  • Driveway planning underway

  • Crane removal scheduled for mid-May

Check back here for monthly construction updates of the project