Progress Report as of June 2026

Residence #1

  • Interior railings, closet systems, and mechanical room ceiling completed

  • Initial cleaning completed after temporary protection removal

  • Fireplace startup underway

  • Elevator passed inspection and is operational

  • Patio heaters and motorized shades being installed

  • Wallpaper and owner-supplied lighting expected to arrive at the end of June

  • Punch list and touch-up work ongoing

Residence #2

  • Stair treads and landings completed

  • Interior railings nearing completion

  • Electrical trim work and LED accent lighting substantially complete

  • Elevator passed inspection

  • Initial cleaning and punch list work to begin shortly

Residence #3

  • Cabinetry, countertops, trim, and doors nearing completion

  • Plumbing fixtures and electrical trim installed

  • Painting and fireplace detailing underway

  • Appliances scheduled for installation next week

Residence #4

  • Wood flooring completed

  • Tile, cabinetry, doors, and trim continue to progress

  • Countertop templating to begin soon

  • Boilers, water tank, and associated plumbing installed

Exterior & Site Work

  • Stucco and masonry work continue across the property

  • Solar panels and gas meters installed

  • Gutters and downspouts underway

  • Hot tub installed at Residence #4

  • Construction crane removed from site

  • Driveway work scheduled to begin in the coming weeks

Check back here for monthly construction updates of the project