Progress Report as of June 2026
Residence #1
Interior railings, closet systems, and mechanical room ceiling completed
Initial cleaning completed after temporary protection removal
Fireplace startup underway
Elevator passed inspection and is operational
Patio heaters and motorized shades being installed
Wallpaper and owner-supplied lighting expected to arrive at the end of June
Punch list and touch-up work ongoing
Residence #2
Stair treads and landings completed
Interior railings nearing completion
Electrical trim work and LED accent lighting substantially complete
Elevator passed inspection
Initial cleaning and punch list work to begin shortly
Residence #3
Cabinetry, countertops, trim, and doors nearing completion
Plumbing fixtures and electrical trim installed
Painting and fireplace detailing underway
Appliances scheduled for installation next week
Residence #4
Wood flooring completed
Tile, cabinetry, doors, and trim continue to progress
Countertop templating to begin soon
Boilers, water tank, and associated plumbing installed
Exterior & Site Work
Stucco and masonry work continue across the property
Solar panels and gas meters installed
Gutters and downspouts underway
Hot tub installed at Residence #4
Construction crane removed from site
Driveway work scheduled to begin in the coming weeks
Check back here for monthly construction updates of the project